Impossible timetables
Published Sun 26 of Aug, 2018 19:43 BST - (4745 Reads) -Toby Hart was a Network Rail train planner based at Leeds. This letter is his submission to the Rail Delivery Group and the Office of Rail and Road inquiry into the disruption following the May 2018 timetable changes. It backs up Railfuture’s contention that Network Rail’s reorganisation of the timetable planning function to reduce costs (at DfT’s direction) and centralise at Milton Keynes contributed to the failure of the timetable through a loss of expertise and insufficient iterations of the timetable process to resolve conflicts in the proposed timetable. Image: Official TfGM Twitter announcement on 19 May 2018.