Railfuture has been campaigning for reinstatement of the railway between Uckfield and Lewes, and building relationships with stakeholders to align them toward that goal. We have been advocating an incremental approach, which is the most likely to succeed within the constraints of Network Rail’s funding and delivery capacity, and be delivered soonest.
Railfuture supports the London and Southern Counties Railways consortium initiative for a second main line from Brighton, leading into a strategic cross-London link, but in reality this will be a mega-project like Crossrail. If the consortium cannot find a commercial business case to justify funding and a technical solution acceptable to DfT, then such a project would inevitably queue for government funding behind Crossrail 2, delaying completion to around 2040 at best.
By contrast, our experience of other reopenings shows incremental approaches delivering new main lines. The fourth mainline between Edinburgh and Glasgow, the double track Airdrie-Bathgate line with fast and frequent electric services, started life as a reopened single track branch from Edinburgh to Bathgate with an hourly 2-car diesel train service. The success of Chiltern's incremental Evergreen phases is legendary.
Network Rail's 2008 Reinstatement Study for the Uckfield-Lewes link succeeded in proving the feasibility of reopening. It failed to prove the business case as its scope was too narrow to generate sufficient benefits; there was no meeting of minds between campaigners and key stakeholders. Since then political priorities and funding sources have changed; regional economic growth is now the top priority for stakeholders, and Local Enterprise Partnerships are a new source of transport project funding which could contribute to GRIP studies.
Railfuture appointed independent adviser JRC to assist with re-energising the interest of key stakeholders and mobilising their active support around a shared vision of regional economic growth in the Sussex coast and Weald, enabled by better travel links between communities and principal economic centres. Unlike the previous study's narrow focus on local benefits, our approach considers broader economic and transport needs in and around Sussex to generate sufficient benefits, and the buy-in of a range of stakeholders. The Jonathan Roberts report, Access and Connections: East Sussex, was instrumental in gaining stakeholder support and underpins the London and South Coast Rail Corridor study report.
The London and South Coast Rail Corridor study by WSP recommended a new approach, led by the LEP and local authorities, with three stages:
1. Improve access. Improving access to stations, for example by building the new Uckfield station car park, will attract more passengers to use the route in preference to others, relieving the Brighton Main Line and increasing the profile of the line with the rail industry, politicians and the public. The car park opened in 2015. Read our article A Platform for Growth.
2. LUCKy Lewes Horseshoe. Events at Dawlish in 2014 showed the need for alternative routes to provide network resilience. A simple loop at Lewes, following the A27 Lewes bypass and the Cockshut, could be completed in Control Period 6 (or sooner) to provide an alternative route between Brighton and Haywards Heath without reversing, which would have enabled a service to be maintained when Patcham Tunnel was flooded recently, and would enable direct services between Falmer and London. It would also avoid reversing of the Lewes - Brighton shuttle service at Lewes, which might improve stock utilisation, and would facilitate services via a reopened Uckfield – Lewes line to Brighton. The radius of curvature is similar to that of the new curve on the East London Line Extension at Shoreditch, which operates without disturbing local residents.
3. Reinstate Uckfield – Lewes. Railfuture agree that the constraints of flat line junctions and fast line platforms at the London end of the Brighton Main Line need to be addressed in Control Period 6 (2019-24), but we contend that Uckfield - Lewes reinstatement can be progressed in parallel, early in Control Period 6. This would give:
4. Tunbridge Wells. An agreement with the Spa Valley Railway would enable direct services to be run between Tunbridge Wells and Brighton.
5. Electrify. Electrification will enable longer trains to run on the Uckfield line , will shorten journey times and will improve reliability. DfT are unable to decide between AC or DC electrification, but the delay to the electrification programme announced in June 2015 strengthens the case for DC electrification, because it can be achieved sooner and will release diesel carriages that will be needed to mitigate the increased shortage of diesel passenger trains which will result from the delay to the AC electrification programme.
6. Redouble. Clearing East Croydon and Clapham Junction bottlenecks and renewal of BML signalling scheduled by Network Rail for 2023 will allow 6 more BML trains per hour, 4 to Victoria and 2 to London Bridge. These London Bridge trains should run via a redoubled Uckfield line between London and the South Coast. Redoubling the Uckfield line (at the same time as resignalling in Control Period 7) would enable a more frequent service which would encourage more passengers to use the Uckfield line in preference to other routes. It would also give:
New approach to Uckfield | Need for Uckfield-Lewes | Solution for Uckfield-Lewes | Uckfield business case | Uckfield-Lewes campaign plan | Background to the Uckfield Lewes campaign
Railfuture supports the London and Southern Counties Railways consortium initiative for a second main line from Brighton, leading into a strategic cross-London link, but in reality this will be a mega-project like Crossrail. If the consortium cannot find a commercial business case to justify funding and a technical solution acceptable to DfT, then such a project would inevitably queue for government funding behind Crossrail 2, delaying completion to around 2040 at best.
By contrast, our experience of other reopenings shows incremental approaches delivering new main lines. The fourth mainline between Edinburgh and Glasgow, the double track Airdrie-Bathgate line with fast and frequent electric services, started life as a reopened single track branch from Edinburgh to Bathgate with an hourly 2-car diesel train service. The success of Chiltern's incremental Evergreen phases is legendary.
Network Rail's 2008 Reinstatement Study for the Uckfield-Lewes link succeeded in proving the feasibility of reopening. It failed to prove the business case as its scope was too narrow to generate sufficient benefits; there was no meeting of minds between campaigners and key stakeholders. Since then political priorities and funding sources have changed; regional economic growth is now the top priority for stakeholders, and Local Enterprise Partnerships are a new source of transport project funding which could contribute to GRIP studies.
Railfuture appointed independent adviser JRC to assist with re-energising the interest of key stakeholders and mobilising their active support around a shared vision of regional economic growth in the Sussex coast and Weald, enabled by better travel links between communities and principal economic centres. Unlike the previous study's narrow focus on local benefits, our approach considers broader economic and transport needs in and around Sussex to generate sufficient benefits, and the buy-in of a range of stakeholders. The Jonathan Roberts report, Access and Connections: East Sussex, was instrumental in gaining stakeholder support and underpins the London and South Coast Rail Corridor study report.
The London and South Coast Rail Corridor study by WSP recommended a new approach, led by the LEP and local authorities, with three stages:
- Identify growth scenarios (productivity, housing and employment)
- Define what rail service is needed
- Assess engineering feasibility and business case
- be value-for-money and affordable, with a viable business case
- meet identified economic, social and transport needs
- be opened in a foreseeable timescale
- deliver stakeholder-agreed regional economic growth benefits
- command the respect and active support of a strategic alliance of political and industry stakeholders.
Step by step
A possible incremental approach to improving services on the Uckfield line and extending services to the South Coast might be:1. Improve access. Improving access to stations, for example by building the new Uckfield station car park, will attract more passengers to use the route in preference to others, relieving the Brighton Main Line and increasing the profile of the line with the rail industry, politicians and the public. The car park opened in 2015. Read our article A Platform for Growth.
2. LUCKy Lewes Horseshoe. Events at Dawlish in 2014 showed the need for alternative routes to provide network resilience. A simple loop at Lewes, following the A27 Lewes bypass and the Cockshut, could be completed in Control Period 6 (or sooner) to provide an alternative route between Brighton and Haywards Heath without reversing, which would have enabled a service to be maintained when Patcham Tunnel was flooded recently, and would enable direct services between Falmer and London. It would also avoid reversing of the Lewes - Brighton shuttle service at Lewes, which might improve stock utilisation, and would facilitate services via a reopened Uckfield – Lewes line to Brighton. The radius of curvature is similar to that of the new curve on the East London Line Extension at Shoreditch, which operates without disturbing local residents.
3. Reinstate Uckfield – Lewes. Railfuture agree that the constraints of flat line junctions and fast line platforms at the London end of the Brighton Main Line need to be addressed in Control Period 6 (2019-24), but we contend that Uckfield - Lewes reinstatement can be progressed in parallel, early in Control Period 6. This would give:
- 33% more peak East Coastway - London capacity without redoubling the Uckfield line, enabling direct Newhaven/Seaford peak services to London
- a direct hourly service between between Kent, Surrey, the Weald, Lewes, and Brighton for education and jobs, using the Lewes Horseshoe
- an off-peak diversionary route (along with the Arun chord) to enable uninterrupted access for visitors to Brighton when BML closed, protecting the Brighton economy. This would also make it much easier for Network Rail to plan and implement the maintenance work which is so necessary to keep the Brighton Main Line running.
- reduced traffic congestion around Lewes and Brighton.
4. Tunbridge Wells. An agreement with the Spa Valley Railway would enable direct services to be run between Tunbridge Wells and Brighton.
5. Electrify. Electrification will enable longer trains to run on the Uckfield line , will shorten journey times and will improve reliability. DfT are unable to decide between AC or DC electrification, but the delay to the electrification programme announced in June 2015 strengthens the case for DC electrification, because it can be achieved sooner and will release diesel carriages that will be needed to mitigate the increased shortage of diesel passenger trains which will result from the delay to the AC electrification programme.
6. Redouble. Clearing East Croydon and Clapham Junction bottlenecks and renewal of BML signalling scheduled by Network Rail for 2023 will allow 6 more BML trains per hour, 4 to Victoria and 2 to London Bridge. These London Bridge trains should run via a redoubled Uckfield line between London and the South Coast. Redoubling the Uckfield line (at the same time as resignalling in Control Period 7) would enable a more frequent service which would encourage more passengers to use the Uckfield line in preference to other routes. It would also give:
- 33% more peak capacity for both East and West Coastway to London
- direct trains throughout the day between London and Newhaven (avoiding splitting/joining Newhaven services at Lewes), supporting regeneration
- a direct twice hourly service between Kent, Surrey, the Weald, Lewes, and Brighton for education and jobs, using the Lewes Horseshoe
- a greater level of network resilience which would have enabled a service to be maintained when Balcombe Tunnel was flooded.
Register your support for electrification and reopening Uckfield - Lewes here!